IN THE HIGH COURT OF ORISSA AT CUTTACK W.P.(C) No. 32670 of 2026 CNR No. ODHC010763292026 Chudamani Satnami & Anr. ..…... Petitioner (s) Mr. Dhananjaya Mund, Adv. -VersusState of Odisha & Ors.
.. .….
Opposite Party (s) Mr. Sonak Mishra, ASC
CORAM: HON’BLE DR. JUSTICE SANJEEB K PANIGRAHI HON’BLE MR. JUSTICE CHITTARANJAN DASH ORDER 29.10.2026 Order No. 01. 1. This matter is taken up through hybrid arrangement. 2. Heard learned counsel for the Petitioners and learned Additional Standing Counsel (ASC) for the State. 3. By filing the present Writ Petition, the Petitioners have sought for a direction to the Opposite Parties to sanction and disburse the compensation amount in favour of the Petitioners’ family for acquisition of land for construction of canal under Upper Indravati Irrigation Project as per the judgment and order dated 05.01.2018 passed by the learned Civil Judge (Senior Division), Dharamgarh in L.A.R. Case No.71 of 2014 within a stipulated time.
4. Learned counsel for the Petitioners submits that Petitioners have filed an application under Section 18 of the L.A. Act for higher compensation, which was referred to the Civil Court for adjudication. The Civil Court registered it as L.A.R. No.71 of 2014 and
same
was
disposed
of
on
05.01.2018
and
higher
compensation was awarded. However, no action has been taken as yet for sanction and disbursement of the compensation amount. He further contends that a similar Writ Petition bearing W.P.(C) No.24619 of 2026 has been disposed of on 16.09.2026 directing Opposite Party No.1 to sanction the amount at an early stage and to take expeditious step for disbursement of the compensation amount. He also submits that the present Writ Petition may be disposed of in terms of the order passed in that Writ Petition. 5. Learned Additional Standing Counsel (ASC) for the State has also no objection to the aforesaid submission made by learned counsel for the Petitioners. 6. In view of the above, we dispose of the Writ Petition with a direction to Opposite Party No.1- Secretary to Government, Department of Water Resources, Bhubaneswar to sanction the amount at an early stage and thereafter the Opposite Party No.3the Special Land Acquisition Officer, Upper Indravati Irrigation
Project, Kusumkhunti, in the District of Kalahandi shall take
expeditious step for disbursement of the compensation amount by end of November, 2026, if there is no other impediment. 7. Issue urgent certified copy of this order as per Rules.