Jog Dass v. Land Acquisition Officer NHAI and Others

Court
High Court of Himachal Pradesh
Date of judgment
19 November 2026
Judge
Justice Romesh Verma
Case number
ARB.C No. 266 of 2026
Result
Allowed
Advocates
Maan Singh
Subject
Civil, Property & land, Arbitration

Download the official PDF

Case at a glance

Jog Dass v. Land Acquisition Officer NHAI and Others was decided by the High Court of Himachal Pradesh on 19 November 2026 in ARB.C No. 266 of 2026. Result: Allowed.

What did the court decide?

Result: Allowed.

In view of aforesaid discussion and taking into consideration the attending facts and circumstance of the instant case, the Arbitrator-cum-Divisional Commissioner, Mandi, H.P., exercising the powers of Arbitrator under Section 3 of the National Highways Act, 1956 is directed to conclude the arbitral proceedings and to pass the arbitral award in Reference Petition No. 205/2023, titled as Jog Dass vs. Land Acquisition Officer, NHAI, on or before 19.05.2027. The petition stands disposed of in the aforesaid terms. 19.11.2026 (pankaj) (Romesh Verma)

From the judgment of the judgment.

Important paragraphs

From the judgment: This Court is of the view that when a statute envisages an authority, be it an Arbitrator, to do a particular act in a particular manner and in a prescribed time schedule, then the onus is upon the said authority/Arbitrator to perform the task entrusted to it within the time schedule prescribed in the statute. The delay, if any, has to be bonafide and explainable. However, in the present petition even after completion of the pleadings, the Arbitrator has closed the proceedings since the time limit for arbitral proceedings to pass an award had elapsed.

The text above is quoted from the judgment itself. Read the full judgment below before relying on it.

Full judgment

2026:HHC:50133 IN THE HIGH COURT OF HIMACHAL PRADESH SHIMLA Arb. Case No. 266/2026 Decided on: 19.11.2026 Jog Dass …..Petitioner Versus The Land Acquisition Officer & ors. ….Respondents

Coram: The Hon’ble Mr. Justice Romesh Verma, Judge. Whether approved for reporting?1

For the Petitioner:

Mr. Maan Singh, Advocate.

For the Respondents: Mr. Diwakar Dev Sharma, Addl. A.G. for respondent Nos. 1 and 3. Mr. Vaibhav Kanwar, Advocate, for respondent No.2.

Romesh Verma, Judge (oral) The present petition under Section 29-A (4) of the Arbitration and Conciliation Act, 1996 has been filed by the petitioners seeking extension of time for completion of the arbitration proceedings in Reference Petition No. 205/2023, titled as Jog Dass vs. Land Acquisition Officer, NHAI, pending before the Divisional Commissioner, Mandi, exercising the powers of Arbitrator under Section 3 of the National Highways Act, 1956.

1Whether reporters of the local papers may be allowed to see the judgment? Yes.

The arbitral dispute has arisen out of the land acquired in District Kullu, H.P. for the purpose of construction of the National Highway, land for which has been acquired under the provisions of National Highways Act, 1956.

Feeling aggrieved by the award passed by the competent authority, the landowner has preferred Arbitration Reference Petition No. 205/2023, before the Arbitrator-cumDivisional Commissioner, Mandi, H.P., and non adjudication of the arbitral proceedings within the statutory period has resulted in filing of the instant petition.

The Reference Petition against the Award was filed by the landowner in the year 2023. According to the petitioner, on account of unforeseen circumstances in the case, which resulted in unnecessary delay in the announcement of the award by the Arbitrator.

This Court has gone through the material available on record carefully and finds that the proceedings have been conducted by the Arbitrator in violation of statutory provisions, as contained in the Arbitration and Conciliation Act, 1996. This Court is of the view that when a statute envisages an authority, be it an Arbitrator, to do a particular act in a particular manner and in a prescribed time schedule, then the onus is upon the said authority/Arbitrator to perform the task entrusted to it within the time schedule prescribed in the statute. The delay, if any, has to be bonafide and explainable. However, in the present petition even after completion of the pleadings, the Arbitrator has closed the proceedings since the time limit for arbitral proceedings to pass an award had elapsed.

In view of aforesaid discussion and taking into consideration the attending facts and circumstance of the instant case, the Arbitrator-cum-Divisional Commissioner, Mandi, H.P., exercising the powers of Arbitrator under Section 3 of the National Highways Act, 1956 is directed to conclude the arbitral proceedings and to pass the arbitral award in Reference Petition No. 205/2023, titled as Jog Dass vs.

Land Acquisition Officer, NHAI, on or before 19.05.2027.

The petition stands disposed of in the aforesaid terms.

19.11.2026 (pankaj)

(Romesh Verma) Judge