M/s.cmk Projects (p)ltd., v. Madurai City Municipal Corporation
- Court
- Madras High Court
- Date of judgment
- 28 October 2026
- Judge
- Justice Mrs L.victoria Gowri
- Case number
- WP(MD) No. 29236 of 2026
- Result
- DISPOSED OF
- Acts & sections
- Article 226 Constitution
- Advocates
- Mr.P.J. Rishikesh, Mr.T.S.Mohammed Mohideen
Full judgment
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 28-10-2026 CORAM THE HON'BLE MRS. JUSTICE L.VICTORIA GOWRI CNR:{HCMD011447922026}
and W.M.P(MD)No.22194 of 2026 M/s.CMK Projects (P)Ltd., Rep. By Its Executive Director, Mr. R. Jagadeesan. ..Petitioner(s) Vs 1. Madurai City Municipal Corporation Rep by its Commissioner, Arignar Anna Maaligai, Thallakulam, Madurai - 625 002. 2. The City Engineer, Madurai City Municipal Corporation, Arignar Anna Maaligai, Thallakulam, Madurai - 625 002. ..Respondent(s) PRAYER: Writ Petition, filed under Article 226 of the Constitution of India, praying this court to issue a Writ of Mandamus directing the Respondents to release the certified and unpaid final-bill amount of Rs. 1,64,60,052/- under Work Order ROC NO.E6/008889/2023 dated 15.09.2023, together with interest at such rate as this Court deems fit from the date of the final-bill payment fell due until realisation.
For Petitioner(s)
:Mr.P.J. Rishikesh
For Respondent(s)
:Mr.T.S.Mohammed Mohideen Standing Counsel For R1 And R2
ORDER
Seeking to direct the respondents to release the certified and unpaid final-bill amount of Rs.1,64,60,052/- under Work Order ROC NO.E6/008889/2023 dated 15.09.2023, together with interest from the date of the final-bill payment fell due until realisation, this writ petition is filed.
2. The petitioner company was engaged in construction work with the 1st respondent Municipal Corporation which was awarded by work order, dated 05.09.2023. Even after completion of the said work, the final bill
amount
of
Rs.1,64,60,052/-
under
work
order
ROC
NO.E6/008889/2023 dated 15.09.2023, is not released so far. Hence, this writ petition.
3. The learned Standing Counsel appearing for the respondents submitted that an amount of Rs.1,92,66,831/- was paid and an amount of Rs.1,62,49,178/- is to be paid and already proper steps have been taken and the communication is also sent to the competent authority, and the petitioner's amount will be disbursed shortly.
4. Heard the learned counsel on either side and carefully perused the materials available on record.
5. In view of the above submission, the respondents are directed to settle the petitioner's unpaid final bill within a period of three (3) months from the date of receipt of copy of this order.
6. With the above directions, this Writ Petition stands disposed of. No costs. Consequently, connected Miscellaneous Petition is closed.
28-10-2026 Index: Yes/No Speaking/Non-speaking order Neutral Citation: Yes/No gbg To 1. Madurai City Municipal Corporation Rep by its Commissioner, Arignar Anna Maaligai, Thallakulam Madurai - 625 002 2. The City Engineer Madurai City Municipal Corporation Arignar Anna Maaligai, Thallakulam Madurai - 625 002
L.VICTORIA GOWRI, J. gbg
28-10-2026