Monu Gond v. State of U.P. and 4 Others

Court
Allahabad High Court
Date of judgment
1 November 2026
Judge
Justice Gautam Chowdhary
Case number
NA528 No. 45344 of 2026
Acts & sections
Section 135 Electricity Act, Section 152 Electricity Act, Section 528 BNSS, Section 528 BNS
Subject
Electricity, Criminal

Download the official PDF

Full judgment

HIGH COURT OF JUDICATURE AT ALLAHABAD APPLICATION U/S 528 BNSS No. - 45344 of 2026

Monu Gond .....Applicant(s) Versus

State Of U.P. And 4 Others .....Opposite Party(s) Counsel for Applicant(s) Counsel for Opposite Party(s)

: :

Chandra Prakash Misra G.A.

Court No. - 73

HON'BLE DR. GAUTAM CHOWDHARY, J. 1. Heard learned counsel for applicant, learned counsel counsel for the Power Corporation, as well as learned A.G.A. for the State and perused the material brought on record. 2. This application under Section 528 B.N.S.S. has been filed with the prayer to set aside the cognizance/summoning order dated 29.07.2025 as well as for quashing of the charge sheet dated 16.11.2023 including the entire proceeding of Criminal Case No. 1037 of 2025, State Vs. Monu Gond, arising out of Case Crime No. 44 of 2021, under Section 135 of Electricity Act (Amendment) 2003, Police Station Anti Theft, District Kushinagar, pending in the court of Additional District & Session Judge Court no.-III, Kushinagar at Padrauna. 3. Learned counsel for the applicant submits that since offence in question is compoundable and the applicant is ready to settle the matter, therefore, some time may be granted to him for the said purpose and to approach the authority concerned under Section 152 of the Electricity Act. 4. Learned counsel for the Power Corporation as well as learned A.G.A. has no objection, if the offence is compounded under the relevant provision of the Electricity Act. 5. Having regard to the facts and circumstances of case and having considered the submissions made by learned counsel for parties and keeping in view the willingness shown by learned counsel for applicant, this Court is of the view that no useful purpose would be served by keeping this application pending. 6. In view of above, it is provided that in case, the applicant moves an application for compounding under the relevant provisions of Electricity Act before the concerned authority within two weeks from today along with the certified copy of this order before the authority concerned, the same shall be considered and decided by the authority concerned as expeditiously as possible in accordance with law, preferably within a period of six weeks months from the date of production of same after hearing the parties concerned.

NA528 No. 45344 of 2026

7. For a period of two months or till the disposal of said application, whichever is earlier, no coercive action shall be taken against applicant in the aforesaid case. 8. In case of default on the part of applicant, interim protection granted to applicant shall automatically come to an end. 9. With the aforesaid observations, this application stands finally disposed of.

(Dr. Gautam Chowdhary,J.)

November 2, 2026 CP.sahani

Digitally signed by :CHANDRA PRAKASH SAHANI High Court of Judicature at Allahabad

Related judgments

More Allahabad High Court judgments

Search all Supreme Court and High Court judgments