N.prema v. The District Collector,
- Court
- Madras High Court
- Date of judgment
- 5 November 2026
- Bench
- Justice Mr S. M. Subramaniam, Justice R.rajesh Vivekananthan
- Case number
- WP No. 44630 of 2026
- Result
- DISPOSED OF
- Acts & sections
- Article 226 Constitution
- Advocates
- Mr.A.E.Ravichandran, Mr.K.Surender
Full judgment
IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 05-11-2026 CORAM THE HON'BLE MR JUSTICE S. M. SUBRAMANIAM AND THE HON'BLE MR.JUSTICE R.RAJESH VIVEKANANTHAN CNR: {HCMA012574352026}
1. N.Prema 2. M.Vengaimalayan ..Petitioner(s) Vs 1. The District Collector, Coimbatore District, Coimbatore. 2. The Divisional Engineer, State Highways Department (Division 2), Coimbatore south division, Trichy Road, Coimbatore - 641018. 3. The Assistant Divisional Engineer, State Highways Department, unit-4, coimbatore south division, Trichy Road, coimbatore - 641018. 4. The Tahsildar, Madukkarai taluk, Madukkarai taluk office, Coimbatore - 641018. 5. Gomathi 6. Ushakumari 7. Suganya ..Respondent(s)
Writ Petition filed under Article 226 of the Constitution of India issuing writ of mandamus directing the 2 nd respondent herein to remove the encroachments in the Vellaloor-Pothanur State Highway at point no.4/4 to 4/6 at SF No.978, Vellaloor Village, Coimbatore South Taluk, Coimbatore District put up by the respondents 5 to 7 herein, identified in the Firkha Surveyor Report dated 27.08.2026, within a reasonable time as maybe fixed by this Court. For Petitioner(s):
Mr.A.E.Ravichandran
For Respondent(s):
Mr.K.Surender Special Government Pleader ORDER
(Order of the Court was made by S.M.Subramaniam J.)
With reference to the relief as sought for in the present writ petition, learned Special Government Pleader, based on the written instruction given by the Tahsildar, Madhukarai submitted that survey was conducted and road encroachments are identified by the Revenue Authorities. Consequently, report has been submitted to the Assistant Divisional Engineer for initiation of enforcement action.
2. In view of the said position, respondents 2 and 3 are directed to initiate enforcement action by following the procedures as contemplated under the Highways Act and remove the encroachments. The entire exercise is directed to be completed within a period of twelve weeks
from the date of receipt of a copy of this order.
3. With these directions, the writ petition stands disposed of. No costs. Consequently, connected miscellaneous petitions, if any, are closed. (S.M.S.,J.) (R.R.V.,J.) 05-11-2026 Index: Yes/No Speaking/Non-speaking order Neutral Citation: Yes/No GD To 1. The District Collector, Coimbatore District, Coimbatore. 2. The Divisional Engineer, State Highways Department (Division 2), coimbatore south division, Trichy Road, coimbatore - 641018. 3. The Assistant Divisional Engineer, State Highways Department, unit-4, coimbatore south division, Trichy Road, coimbatore - 641018. 4. The Tahsildar, madukkarai taluk, madukkarai taluk office, Coimbatore - 641018.
S.M.SUBRAMANIAM, J. AND R.RAJESH VIVEKANANTHAN, J. GD
05-11-2026