Nav Nirman Seva Sansthan v. State of U.P. and Another

Court
Allahabad High Court
Date of judgment
4 October 2026
Bench
Justice Siddhartha Varma, Justice Kunal Ravi Singh
Case number
WRIC No. 35034 of 2025

Download the official PDF

Full judgment

HIGH COURT OF JUDICATURE AT ALLAHABAD WRIT - C No. - 35034 of 2025

Nav Nirman Seva Sansthan .....Petitioner(s) Versus

State of U.P. and Another .....Respondent(s) Counsel for Petitioner(s) Counsel for Respondent(s)

: Rahul Kumar Jadaun : Anand Prakash Paul, C.S.C., Shiv Prakash Gupta

Court No. - 29

HON'BLE SIDDHARTHA VARMA, J. HON'BLE KUNAL RAVI SINGH, J.

1. The petitioner was granted a lease for construction of a building on 13.11.2018 and the construction had to be completed within 5 years of the execution of the lease. On 21.12.2022, the petitioner's map was sanctioned and then as per it, construction had to be completed as per the lease-deed by 12.11.2023. When the construction was not completed by that date, the petitioner approached the Revisional Authority which on 3.9.2024 had remanded the matter requesting the Development Authority to condone the period, during which nation was going through COVID-19 Pandemic and then accordingly grant relaxation. However, on 21.8.2025 when the order was passed granting the petitioner only one year of relaxation for the construction, the petitioner approached this Court. 2. Learned Counsel appearing for the petitioner states that as per the Revisional Authority order dated 3.9.2024, a relaxation of atleast 2 years for the completion of construction ought to have been given. It is submitted that the clause provided in the lease-deed that the construction had to take place within 5 years from 13.11.2018 could not have been pressed as there was an intervening COVID-19 pandemic in the country. 3. Sri A.P. Paul, learned Counsel appearing for Development Authority, however, states that the petitioner did not commence the construction since the map itself was got sanctioned on 21.12.2022. He was, therefore, not entitled for any relaxation whatsoever and one year relaxation which had been given was sufficient and was due compliance of the order of

WRIC No. 35034 of 2025

Revisional Authority dated 3.9.2024. 4. Having considered the rival submissions, we are of the view that when the lease was executed on 13.11.2018 and the construction had to take place within 5 years, the petitioner definitely could not have applied for the map during the intervening period as the COVID-19 Pandemic began in the month of April, 2019 and continued for 2 years and, therefore, when the petitioner had applied on 21.12.2022 then the period exempted under the COVID-19 Pandemic had to be excluded. 5. Under such circumstances, we are of the view that the impugned order dated 21.8.2025 cannot be sustained and the same is quashed and the matter is remitted back to the Vice Chairman for a fresh consideration of the matter taking into consideration the order dated 27.5.2025 passed in Writ-C No.17201 of 2025 as well as the order of Revisional Authority dated 03.09.2024. 6. In view of what has been stated herein above and what was was stated in the order of the Revisional Authority dated 3.9.2024, the writ petition is partly allowed.

(Kunal Ravi Singh,J.) (Siddhartha Varma,J.)

October 5, 2026 Irshad

Digitally signed by :IRSHAD AHMAD SIDDIQUI High Court of Judicature at Allahabad

Related judgments

More Allahabad High Court judgments

Search all Supreme Court and High Court judgments

Reproduced from the official court copy published on eCourts (Indian Court Judgments open dataset, CC-BY-4.0). Not legal advice.