NHAI v. Competent Authority Cum Collector and Others
- Court
- High Court of Himachal Pradesh
- Date of judgment
- 3 November 2026
- Judge
- Justice Romesh Verma
- Case number
- ARB.C No. 249 of 2026
- Result
- Disposed Off
- Advocates
- Shreya Chauhan, Baldev Singh Negi
- Subject
- Civil, Property & land, Arbitration
Full judgment
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA Arbitration Case No. 249 of 2026 Date of decision : 03.11.2026 NHAI
...Petitioner. Versus
Competent Authority-cum Collector Land Acquisition NHAI & others
...Respondents.
_____________________________________________________________________
Coram:
The Hon’ble Mr. Justice Romesh Verma, Judge. Whether approved for reporting?1
For the Petitioner:
Ms. Shreya Chauhan, Advocate.
For the Respondents:
Mr. Baldev Singh Negi, Additional Advocate General, for respondent No.1. ______________________________________________________________ Romesh Verma, Judge (oral) Since the present petitioner has prayed for extension of time, therefore, at this stage, this Court is not issuing notices for the service of private respondents . 2.
Notice. Mr. Baldev Singh Negi, learned Additional Advocate
General, appears and waives service of notice on behalf of respondent No.1. 3.
The present petition under Section 29 (4) of the Arbitration
and Conciliation Act, 1996 has been filed by the petitioner seeking extension of time for completion of the arbitral proceedings in Reference Petition No. 83 of 2022, titled as National Highway Authority of India vs. Competent Authority-cum- collector Land Acquisition & others, pending
Whether reporters of Local Papers may be allowed to see the judgment?
before the Divisional Commissioner-cum-Arbitrator, Mandi, District Mandi, H.P. exercising the powers of Arbitrator under Section 3 G (5) of the National Highways Act, 1956. 4.
The arbitral dispute has arisen out of the land acquired in
District Mandi, H.P. for the purpose of construction of the National Highway, land for which has been acquired under the provisions of National Highways Act, 1956. 5.
Feeling aggrieved by the award passed by the competent
authority, the petitioner has preferred Arbitration Reference Case No. 83 of 2022 before the Divisional Commissioner-cum-Arbitrator at Mandi, District Mandi, H.P. and non adjudication of the arbitral proceedings within the statutory period has resulted in filing of the instant petition. 6.
The Reference Petition against the Award was filed by the
petitioner in the year 2022. According to the petitioner, on account of unforeseen circumstances in the case, has resulted in unnecessary delay in the announcement of the award by the learned Arbitrator, i.e. the Divisional Commissioner-cum-Arbitrator, Mandi, District Mandi, H.P. 7.
This Court has gone through the material available on
record carefully and finds that the proceedings have been conducted by the Arbitrator in violation of statutory provisions, as contained in the Arbitration and Conciliation Act, 1996. This Court is of the view that when a statute envisages an authority, be it an Arbitrator, to do a
particular act in a particular manner and in a prescribed time schedule, then the onus is upon the said authority/Arbitrator to perform the task entrusted to it within the time schedule prescribed in the statute. The delay, if any, has to be bonafide and explainable. However, in the present petition even after completion of the pleadings, the Arbitrator has closed the proceedings since the time limit for arbitral proceedings to pass an award had elapsed. 8.
In
view
of
aforesaid
discussions
and
taking
into
consideration the attending facts and circumstances of the instant case, the Arbitrator-cum-Divisional Commissioner, Mandi, District Mandi, H.P., exercising the powers of Arbitrator under Section 3 of the National Highways Act, 1956 is directed to conclude the arbitral proceedings and to pass the arbitral award in Arbitration Reference Case No. 83 of 2022, on or before 3rd May, 2027. 9.
The
learned
Arbitrator-cum-Divisional
Commissioner,
Mandi, District Mandi, H.P., is directed to serve private respondents through their counsel, who were representing them before the said authority and after the service of private respondents, the Arbitrator shall proceed in the matter, in accordance with law. The petition stands disposed of in the aforesaid terms.
November 3, 2026 (Nisha)
(Romesh Verma) Judge