IN THE HIGH COURT OF DELHI AT NEW DELHI Date of Decision: 14th October, 2026

% #

CNR No. DLHC010237922023

+

W.P.(CRL) 1751/2023 & CRL.M.A. 16359/2023, CRL.M.A. 16492/2023, CRL.M.A. 16684/2023, CRL.M.A. 16687/2023, CRL.M.A. 28220/2023, CRL.M.A. 28274/2023, CRL.M.A. 2901829019/2023, CRL.M.A. 29068-29071/2023, CRL.M.A. 29103/2023, CRL.M.A. 29107-29108/2023, CRL.M.A. 32517-32522/2023, CRL.M.A. 32540-32542/2023, CRL.M.A. 35710/2023, CRL.M.A. 35721-35724/2023, CRL.M.A. 3308/2024, CRL.M.A. 6504/2024, CRL.M.A. 16617/2024, CRL.M.A. 18392-18393/2024, CRL.M.A. 30931/2024, CRL.M.A. 31036/2024, CRL.M.A. 33640/2024, CRL.M.A. 27816-27817/2025, CRL.M.A. 11691-11692/2026, CRL.M.A. 21593/2026, CRL.M.A. 29769/2026 ROOP BANSAL & ORS. Through:

.....Petitioners Mr. Rajat Joneja, Mr. Avishkar Singhvi, Mr. Yash Varma, Mr. Vivek Kumar Singh, Advocates M: 9711179388 Email: chamber.rajatjoneja@gmail.com

versus UNION OF INDIA & ORS. Through:

.....Respondents Mr. Vivek Gurnani, Panel Counsel for ED with Mr. Kanishk Maurya, Advocate Email: vivek.gurnani14@gmail.com

CORAM: HON’BLE MS. JUSTICE MINI PUSHKARNA MINI PUSHKARNA, J. (Oral): 1.

The present writ petition was filed in the year 2023 under Article 226

of the Constitution of India, 1950 (“Constitution”) read with Section 482 of the Code of Criminal Procedure, 1973 (“CrPC”), with the following prayers: “xxx xxx xxx

xxx xxx xxx” 2.

Learned counsel appearing for the petitioners submits that as far as

prayer (a) is concerned, the same has already become infructuous, as the same pertained to summons dated 06th June, 2023, for personal appearance of petitioner nos. 1 and 2, on 07th June, 2023, by the respondents. 3.

Accordingly, it is noted that the present petition has already become

infructuous as far as prayer (a) is concerned. 4.

As regards prayer (b), this Court notes that subsequently, the

Directorate of Enforcement (“ED”) vide Provisional Attachment Order dated 17th July, 2026, has attached various land parcels belonging to the petitioners to the tune of Rs. 404,00,00,000/- (Rupees Four Hundred and Four Crores only). 5.

Thus, the said Provisional Attachment Order passed by the ED, reads

as under:

“xxx xxx xxx

”

6.

This Court notes the submission made by learned counsel appearing

for the petitioners that the land parcels, attached by the ED, are free from any encumbrances and are owned by the petitioners. 7.

In this regard, the petitioners have also filed an Affidavit dated 19th

September, 2026, along with CRL.MA. 29769/2026, which is reproduced as under: “

8.

This Court notes that with respect to the provisional attachment order,

the ED in its Counter Affidavit dated 24th August, 2026, has stated as under:

“xxx xxx xxx

xxx xxx xxx”

9.

Perusal of the aforesaid Counter Affidavit and the Provisional

Attachment Order dated 17th July, 2026, clearly shows that the ED has already provisionally attached properties to the value of Rs. 404,00,00,000/(Rupees Four Hundred and Four Crores) of the petitioners, i.e., M3M Group of Companies. 10.

A search under Section 17 of the PMLA was conducted on 01st July,

2023, at the business and residential premises of the M3M Group and its owners/promotes, i.e., petitioner nos. 1 to 3. The seizure of properties, thus, made by ED previously, which are subject matter of the present petition, have been enumerated in Table nos. 1 to 4, in the said Counter Affidavit of the ED, as follows:

“xxx xxx xxx

xxx xxx xxx” 11.

Further, the ED has also stated that the seized cash, jewellery and

vehicles/fixed deposits, are no longer part of the investigation in the instant case. 12.

Accordingly, considering the submissions made before this Court, it is

directed that the assets as belonging to M3M Group of Companies as detailed in the aforesaid tables, i.e., Table 1, 2, 3 and 4, shall be released forthwith to the petitioners/authorised representatives of the petitioners. 13.

Furthermore, considering the fact that the ED has already secured the

amount of Rs. 404,00,00,000/- (Rupees Four Hundred and Four Crores) by way of Provisional Attachment Order dated 17th July, 2026, it is directed that the title deeds of the parcel of land as deposited by the petitioners in terms of the order dated 12th June, 2023, passed in the present proceedings, shall be released forthwith to the petitioners. 14.

It is clarified that in terms of the submission made by learned counsel

appearing for the petitioners, the said parcel of lands whose title deed were deposited in terms of order dated 12th June, 2023, do not form subject matter of the Provisional Attachment Order dated 17th July, 2026 of the ED. 15.

Needless to state that the order passed today is not any expression on

merit of the Provisional Attachment Order dated 17th July, 2026 of the ED or the pendency of the proceedings against the M3M Group of Companies. 16.

With the aforesaid directions, the present petition is disposed of.

17.

Pending applications are also disposed of.

MINI PUSHKARNA, J OCTOBER 14, 2026 ak