Rudrapur Institute of Technology v. State of Uttarakhand
- Court
- High Court of Uttarakhand
- Date of judgment
- 31 October 2026
- Judge
- Justice Pankaj Purohit
- Case number
- WPMS No. 3316 of 2026
- Result
- DISPOSED
Full judgment
HIGH COURT OF UTTARAKHAND AT NAINITAL Writ Petition Misc. Single No. 3316 of 2026 31st October, 2026
Rudrapur Institute Of Technology --Petitioner
Versus
State Of Uttarakhand 2: Labour Commissioner 3: Secretary 4: Assistant Labour Commissioner --Respondent ---------------------------------------------------------------------Presence:Mr. Harsh Vardhan Dhanik, Advocate for the petitioner. Ms. Mamta Bisht, Deputy Advocate General for the State. Mr. Hari Mohan Bhatia, Advocate for respondent no.3.
----------------------------------------------------------------------
Hon'ble Pankaj Purohit, J.
Petitioner is aggrieved by the order passed by Assistant Labour Commissioner-cum-Cess Assessor and Cess Collector, under Section 5 of the Building and Other Construction
Workers’
Welfare
Cess
Act,
1996,
(hereinafter referred to as ‘the Act’) whereby, petitionerConstruction Company is directed to pay the penalty and labour cess. 2.
Feeling aggrieved by the said order, petitioner
has approached the Appellate Authority i.e. Labour Commissioner, Uttarakhand, under Section 11 of the Act by filing Appeal.
A prayer has been made by petitioner for staying the operation and effect of the orders impugned passed by learned Assistant Labour Commissioner in the said Appeal. 3.
It
is
contended
by
learned
counsel
for
petitioner that due to non-availability of the Presiding Officer i.e. Assistant Labour Commissioner-cum-Cess Assessor and Cess Collector in the office, prayer for interim relief/stay is still pending, causing hardship to petitioner, as the amount assessed in the impugned orders under Section 5 of the Act, would be recovered by respondents with penalty, despite filing the Appeal. Thus, petitioner approached this Court seeking a direction to Appellate
Authority
i.e.
Labour
Commissioner,
Uttarakhand, to consider and grant the prayer for interim relief/stay
to
petitioner
within
stipulated
time
as
prescribed by this Court. 4.
Learned counsel for petitioner submits that if
such a direction is issued to Appellate Authority i.e. Labour Commissioner, Uttarakhand, the grievance of petitioner would be redressed. 5.
This fact is not disputed by learned counsel for
State and counsel for respondent No.3-Uttarakhand Building
and
Other
Construction
Workers’
Welfare
Board. 6.
Having considered the facts of the case as put
forward in the writ petition and having gone through the impugned orders, this Court is of the view that since the Appeal is pending disposal, a direction can be issued to
Appellate
Authority
i.e.
Labour
Commissioner,
Uttarakhand, to consider and decide the interim relief prayer of petitioner in the Appeal expeditiously. 7.
Accordingly, this writ petition is disposed of
directing
learned
Appellate
Authority
i.e.
Labour
Commissioner, Uttarakhand, to consider and decide petitioner’s interim relief application made in appeal as expeditious as possible but not later than fifteen days from today. 8.
Learned
counsel
for
respondent
No.3-
Uttarakhand Building and Other Construction Workers’ Welfare Board made a submission before this Court that till the interim relief prayer of petitioner is considered by the Appellate Authority, no recovery shall be made from the petitioner. 9.
Pending application(s), in all writ petitions,
stands disposed of.
(Pankaj Purohit, J.) 31.10.2026
Ravi