HIGH COURT OF MEGHALAYA AT SHILLONG WP(C). No. 494 of 2026 MLHC010018782026 Date of Decision: 06.11.2026 Uploaded on: 06.11.2026 ____________________________________________________________ Shri. Shashikumar Bhagat, S/o Shri. T.G.Bhagat, Resident of Lapalang, Shillong, East Khasi Hills District, Meghalaya. …Petitioner -Versus1.

Grid Controller of India Ltd., B-9 (1st Floor), Qutab Institutional Area, Katwaria Sarai, New Delhi – 110016. Represented by its Chairman/Managing Director.

2.

North Eastern Regional Load Dispatch Centre, Lower Nongrah, Lapalang, Shillong, Meghalaya, represented by its Chief General Manager, NERLDC, Shillong.

3.

The Chief General Manager (MO&SO), NERLDC, Shillong, East Khasi Hills District, Meghalaya.

4.

The Chief General Manager (Logistics), NERLDC, Shillong, East Khasi Hills District, Meghalaya.

5.

The Dy. General Manager (HR), Grid India (Shillong), RHQ, NERTS, POWERGRID, Shillong, East Khasi Hills District, Meghalaya.

6.

Shri. Mintu Mondal, presently posted as Dy. General Manager (Market Operations), NRLDC, Grid Controller of India Ltd., 18 A, Shaheed Jeet Singh Sansanwal Marg, New Delhi, India.

7.

Smti. Gargi Dutta, presently posted as Dy. General Manager (Corporate Centre), Grid Controller of India Ltd., R/o Qtr. No. C/11, Powergrid Colony, Lower Nongrah, Lapalang, Shillong, Meghalaya. …Respondents

Coram: Hon’ble Mr. Justice H.S.Thangkhiew, Judge Appearance: For the Petitioner/Applicant(s) :

For the Respondent(s)

i) ii)

:

Mr. S.Deb, Adv. Ms. S.G.Marpna, Adv. -

Whether approved for reporting in Law Journals etc: Whether approved for publication in press:

Yes/No Yes/No

JUDGMENT (ORAL): 1.

Heard Mr. S.Deb, learned counsel for the petitioner.

2.

The petitioner, being aggrieved with the show cause notice dated 11-

09-2026, is before this Court praying for appropriate orders. 3.

Mr. S.Deb, learned counsel for the petitioner has submitted that the

incidents that had given rise to the show-cause notice never occurred, and

that the dispute is between two employees. He further submits that the showcause was never served on the petitioner and it was received by the petitioner only on 16-10-2026. He also submits that though 15 days’ time was prayed to reply to the same, there has been no response from the respondents. 4.

This Court has heard the learned counsel for the petitioner. From the

show-cause notice it appears that the allegations are serious in nature. However, as it is submitted that there has been no response on the prayer for time to give a proper reply, at this stage itself, this Court in consideration of the facts, directs the petitioner to file a reply to the show cause notice dated 11-09-2026, within two weeks from the date of this order which will be accepted by the respondents No. 1, 2 & 3, and be taken into consideration. As the matter only concerns a challenge to the show-cause, notice to the official respondents at this stage also is deemed not necessary. As nothing remains for consideration in the instant matter, the writ petition is closed and disposed of.

Judge

Verified

Digitally signed by:

SAMANTHA ANNA LIYA RYNJAH

Signed On:

06-11-2026 17:29:25 IST

Related judgments

More Meghalaya High Court judgments

Search all Supreme Court and High Court judgments

Reproduced from the official court copy published on eCourts (Indian Court Judgments open dataset, CC-BY-4.0). Not legal advice.