Shyam Bihari v. Chhattisgarh State Power Distribution Company Limited
- Court
- High Court Of Chhattisgarh
- Date of judgment
- 4 October 2026
- Judge
- Justice Shri Bibhu Datta Guru
- Case number
- WPS No. 7232 of 2026
- Result
- DISPOSED OFF
- Advocates
- Bharat Lal Dembra
- Subject
- Electricity, Service
Full judgment
CGHC010387372026
2026:CGHC:42902
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR WPS No. 7232 of 2026 Shyam Bihari S/o Shri Fulchand Suryavanshi Aged About 44 Years Working As Line Attendent (Contract), Padatarai Distribution Centre, (O/m) Division Pandariya, Chhattisgarh State Power Distribution Digitally signed by SHOAIB
SHOAIB ANWAR ANWAR Date:
Company Limited, Pandariya Division, Distt. Kabirdham (C.G.)
2026.10.05 17:08:27 +0530
... Petitioner(s)
versus
1 - Chhattisgarh State Power Distribution Company Limited Through Its Managing Director, Vidyut Sewa Bhawan, Danganiya, Raipur Distt. Raipur (C.G.)
2 - Executive Director (O/m) Chhattisgarh State Power Distribution Company Limited, Vidyut Sewa Bhawan, Danganiya, Raipur Distt. Raipur (C.G.)
3 - The Superintendent Engineer Office Of Executive Director, C.S.P.D.C.L. Vidyut Sewa Bhawan, Daganiya Raipur Distt. Raipur (C.G.)
4 - Assistant Engineer C.S.P.D.C.L. Pandariya Sub-Division, Pandariya Distt. Kabirdham (C.G.)
5 - Executive Engineer C.S.P.D.C.L. Pandariya Division, Pandariya Distt. Kabirdham (C.G.) ... Respondent(s) (Cause title taken from CIS) For Petitioner(s)
: Shri Bharat Lal Dembra, Advocate
For Respondent(s)
: Shri Varun Sharma, Advocate
(Hon’ble Shri Justice Bibhu Datta Guru) Order on Board 05.10.2026 1.
The petitioner has filed the present writ petition seeking, inter alia, a direction to the respondents to give effect to the order of transfer dated 03.01.2025 (Annexure P/1) and to relieve him so as to enable him to join at his transferred place of posting.
2.
Learned counsel appearing for the petitioner submits that the petitioner was initially appointed as a Line Attendant (Contract) in the year 2016. By order dated 03.01.2025, issued by the Executive Director of the (O/M) CSPDCL, Raipur, the petitioner was transferred from Pandatarai Distribution Centre, Office of Executive Engineer (O/M) Division Pandariya to Barpali Distribution Centre, Division Korba and was required to be relieved to enable him to join at the transferred
place. It is submitted that despite the aforesaid order of transfer having been issued by the Executive Director, the petitioner has not been relieved and, consequently, has been unable to join at the place of his transfer. The petitioner has also made a representation in this regard, but no effective action has been taken. Hence, the present petition. 3.
Per
contra,
learned
counsel
for
the
Respondents,
on
instructions, would submit that due to lack of employees in the present place of posting of the petitioner, the petitioner has not been relieved. 4.
I have considered the submissions made and have perused the material available on record.
5.
The short issue which arises for consideration is as to whether the petitioner can be denied the benefit of the transfer order dated 03.01.2025 (Annexure P/1), which continues to remain operative. Perusal of Annexure P/1 clearly shows that the order dated 03.01.2025 has been issued by the Executive Director, whereby the petitioner has been transferred from Pandatarai Distribution Centre, Office of Executive Engineer (O/M) Division Pandariya to Barpali Distribution Centre, Division Korba. The said order is admittedly the order of the
competent authority and, as on date, there is nothing on record to indicate that the same has either been cancelled, modified or otherwise withdrawn by the competent authority. 6.
Once
the
competent
authority
has
passed
an
order
transferring and posting the petitioner at a particular place, and such order continues to remain in force, the respondents cannot keep the same unimplemented indefinitely. The petitioner is required to be relieved so as to enable him to join at the place of posting indicated in the transfer order. It is, of course, for the employer to take appropriate administrative measures regarding the placement and adjustment of its employees, as may be considered necessary in the exigencies of
administration.
However,
such
administrative
considerations cannot, in the absence of any order modifying or cancelling the transfer order, furnish a ground for withholding the relieving of the petitioner and thereby rendering the subsisting order of transfer ineffective. 7.
In the circumstances of the case, this Court is of the considered
view
that
the
petitioner
is
entitled
to
implementation of the order of transfer dated 03.01.2025 (Annexure P/1). The respondents are, therefore, duty-bound
to take necessary consequential steps to relieve the petitioner so as to enable him to join at his transferred place of posting. Accordingly, the respondents are directed to take necessary steps for relieving the petitioner and to facilitate his joining at Barpali Distribution Centre Division Korba, Distt- Korba (C.G.) pursuant to the transfer order dated 03.01.2025 (Annexure P/1), within a period of 20 (Twenty) days from the date of receipt of a copy of this order. 8.
With the aforesaid direction, the writ petition is allowed to the aforesaid extent. Sd/-(Bibhu Datta Guru) JUDGE
Shoaib