Shyamapada Goswami v. The State of West Bengal and ORS.

Court
Calcutta High Court
Date of judgment
8 October 2026
Judge
Justice Partha Sarathi Sen
Case number
WPA No. 13447 of 2025
Result
DISPOSED

Download the official PDF

Full judgment

08.10.2026 Sl. No. 21 (DL) Ct.No.19 (Susanta) (Bench I.D. 266052)

WPA 13447 of 2025 Shyamapada Goswami Vs. The State of West Bengal & Ors. Mr. Rahul Agarwala, Ms. Puja Sonkar, … for the Petitioners. Ms. Jayita Dhar Chakraborty, Mr. Joy Ranjan Dhar, …. For the State. 1. Affidavit of service as filed today on behalf of the writ petitioner is taken on record. 2. The writ petitioner and the respondent State are represented by their respective learned advocates. 3. None

appears

on

behalf

private

respondents despite service. 4. By filing the instant writ petition, the writ petitioner has prayed for the issuance of appropriate writ/writs against the respondent authorities, more specifically

against

jurisdictional

Assistant

Engineer, Public Works Department (PWD) Division, Balurghat, District-Dakshin Dinajpur, to remove the encroachment as allegedly made by the private respondents in front of the writ petitioner’s property, particulars

which

have

been

mentioned

in

paragraph number 3 of the instant writ petition. 5. At the time of hearing, Ms. Sonkar, duly led by Mr. Agarwala, submits before this Court that it is the

specific case of the writ petitioner that on account of such illegal encroachment made by the private respondents over the PWD land, which is contiguous to the writ petitioner’s property, particulars of which have been stated in paragraph 3 of the instant writ petition, the writ petitioner is facing extreme difficulty in getting easy access to his own property. 6. It is submitted further that despite submissions

several

representations

with

respondent

authorities, no action has been taken. 7. It

is

thus

submitted

by

Ms.

Sonkar

that

appropriate relief/reliefs may be granted to the writ petitioner in terms of the prayers of the instant writ petition. 8. Ms.

Dhar

Chakraborty,

learned

advocate

appearing on behalf of the respondent State, submits before this Court that the jurisdictional Assistant Engineer, Public Works Department (PWD) Division,

District-Dakshin

Dinajpur

may

be

directed to consider the representation of the writ petitioner in accordance with law. 9. In view of such, this Court, while disposing of the instant writ petition, passes the following orders:a) The respondent no. 7 authority is hereby directed to serve notice upon the writ petitioner and the private respondents and shall proceed to the disputed plot for the purpose of field verification, and

shall

submit

a

field

verification

report/demarcation report with the jurisdictional

Assistant Engineer, Public Works Department (PWD)

Division,

District-Dakshin

Dinajpur, positively within 30 working days from the date of communication of the server copy of this order. b) The jurisdictional Assistant Engineer, Public Works Department (PWD) Division, Balurghat, District-Dakshin Dinajpur, on receipt of the said field verification report and/or demarcation report from the respondent no. 7 authority, shall cause service of notice upon the writ petitioner and the private respondents and shall provide them the copies of the said demarcation report. c) The said jurisdictional Assistant Engineer is further directed to consider the representation dated 24.04.2025, as submitted by the writ petitioner with the respondent no. 5 authority, in accordance with law and in the light of the demarcation report as would be submitted by the respondent no. 7 authority, and after giving due chance of hearing both to the writ petitioner and the private respondents and/or their authorized representatives, shall pass a reasoned order and shall forthwith communicate the same both to the writ petitioner and the private respondents, preferably by email, if the email details of the writ petitioner

and

private

respondents

provided to him at the time of hearing.

are

10.

The

entire

exercise

as

indicated

hereinabove shall have to be completed by the jurisdictional Department

Assistant (PWD)

Engineer,

Division,

Public

Works District-

Dakshin Dinajpur, positively within 45 working days from the date of receipt of the demarcation report and/or field verification report from the respondent no. 7 authority. 11.

The time limits as fixed by this Court are

peremptory and mandatory. 12.

It is further directed that in the event, while

passing

reasoned

order,

jurisdictional

Assistant Engineer, Public Works Department (PWD) Division, Balurghat,

finds sufficient merit in the

representation

writ

petitioner

dated

24.04.2025, the said Assistant Engineer is directed to take all consequential actions. 13.

Liberty is given to the learned advocate on

record for the writ petitioner to communicate the server copy of this order along with a copy of the representation dated 24.04.2025 to the respondent no.5, respondent no.7 as well as to the jurisdictional Assistant Engineer, Public Works Department (PWD) Division, Balurghat, District-Dakshin Dinajpur, and such authorities are directed to act on the server copies of this order. 14.

With

aforementioned

W.P.A. 13447 of 2025 is disposed of.

observations,

15.

Before parting with, it is, however, made

clear that while disposing of the instant writ petition, this Court has not gone into the merits of the representation dated 24.04.2025 as submitted by the writ petitioner, and thus all points are kept open for adjudication by the aforementioned jurisdictional Assistant Engineer, Public Works Department (PWD) Division, Balurghat.

(Partha Sarathi Sen, J.)