Sri H a Makhtiyar v. The State of Karnataka

Court
High Court of Karnataka
Date of judgment
27 October 2026
Judge
Justice Jyoti M
Case number
WP No. 22024 of 2024
Result
ALLOWED

Download the official PDF

Full judgment

-1HC-KAR

IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 27TH DAY OF OCTOBER, 2026 BEFORE THE HON'BLE MS. JUSTICE JYOTI M WRIT PETITION NO. 22024 OF 2024 (SC/ST) BETWEEN: SRI H A MAKHTIYAR S/O LATE H.A. ABDUL RAHAMAN, AGED ABOUT 53 YEARS, RESIDING AT NO.119, 7TH CROSS, ASHOK NAGAR, TUMAKURU - 572101. …PETITIONER (BY SRI. B C VENKATESH, ADVOCATE) AND: 1.

Digitally signed by PREMCHANDRA M R 2. Location: HIGH COURT OF KARNATAKA

THE STATE OF KARNATAKA REPRESENTED BY ITS PRINCIPAL SECRETARY, REVENUE DEPARTMENT, M.S.BUILDING, BENGALURU - 560001. THE DEPUTY COMMISSIONER CHAMARAJANAGARA DISTRICT DOUBLE ROAD, CHAMARAJANAGAR - 571313

3.

THE ASSISTANT COMMISSIONER KOLLEGALA SUB DIVISION, KOLLEGALA, CHAMARAJA DISTRICT - 571440

4.

THE TAHSILDAR CHAMARAJANAGAR NH-212, KOZHIKODE KERALA HIGHWAY, GUNDLUPETE, KARNATAKA - 571 111 …RESPONDENTS

(BY SMT. SAVITHRAMMA, AGA FOR R1 TO R4)

-2HC-KAR

THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA, SEEKING CERTAIN RELIEFS. THIS WRIT PETITION IS LISTED FOR PRELIMINARY HEARING IN 'B' GROUP, THIS DAY, AN ORDER IS MADE

AS

UNDER:

ORAL ORDER Sri.B.C.Venkatesh., counsel for the petitioner and Smt.Savithramma., Additional Government Advocate for respondent Nos.1 to 4 appeared in person.

In PTCL writ petitions, the orders passed by the Assistant Commissioner and the Deputy Commissioner are ordinarily called into question. This Court has frequently noticed discrepancies in the names of the original grantees and the dates of grant and alienation recorded in the impugned orders. Hence, for the sake of convenience, this Court refers to the parties as the “original grantee” and the relevant years of grant and alienation, instead of reproducing the names and dates.

-3HC-KAR

2.

The petition is filed seeking a writ of certiorari

to quash the orders passed by the Assistant Commissioner and

the

Deputy

Commissioner.

These

orders

are

challenged in this writ petition on several grounds as set out in the memorandum of the writ petition.

3.

Counsel for the respective parties advanced

several contentions.

AGA submits that an appropriate orders may be passed.

4.

The Court heard the arguments and carefully

perused the papers. 5.

This issue is limited to resumption proceedings.

The land in question was granted in 1977-78. The first alienation has taken place in 1995 and the second alienation has taken place in 2007. After purchase of the property, when the petitioner sought change of Khata, the Assistant Commissioner suo motu initiated proceedings

-4HC-KAR

alleging that there is a violations of the provisions of the PTCL Act in 2013. Hence, the Assistant Commissioner ordered resumption of the land and on appeal, the Deputy Commissioner has confirmed the order of the Assistant Commissioner. It is noted that the Assistant Commissioner and the Deputy Commissioner overlooked laches of 18 years. Hence, the resumption of the land cannot be sustained.

The authorities should have evaluated whether to proceed after nearly 18 years, especially since the rights in the land were settled by the sale deed in 1995. The oversight in considering the delay and laches led to orders for land resumption being issued without adequately addressing a crucial and relevant issue.

The Division Bench clarified that laches should be regarded as the primary requirement when resuming lands. It also held that if restoration action is filed after a significant delay, it could be barred by laches.

-5HC-KAR

In the facts and circumstances of the case, this Court is of the considered view that the orders passed by the Assistant Commissioner and confirmed by the Deputy Commissioner, directing resumption of the subject land, cannot be legally sustained. Accordingly, the impugned orders are liable to be set aside.

6.

For the foregoing reasons, the orders of the

Assistant Commissioner and the Deputy Commissioner are liable to be set aside.

7.

The writ of certiorari is ordered. The order

dated 27.08.2018 passed by the Assistant Commissioner vide Annexure-B, and the order dated 11.09.2023 passed by

the

Deputy

Commissioner

vide

Annexure-A

are

quashed. As this Court has quashed the orders, the authority concerned is hereby directed to mutate the petitioner's name in the subject land in the revenue records.

8.

Resultantly, the writ petition is allowed.

-6HC-KAR

On disposal of the Writ Petition, any interim order stands

discharged,

and

any

pending

applications, if any, are disposed of. Sd/(JYOTI M) JUDGE CH List No.: 1 Sl No.: 34

interlocutory

Related judgments

More Karnataka High Court judgments

Search all Supreme Court and High Court judgments

Reproduced from the official court copy published on eCourts (Indian Court Judgments open dataset, CC-BY-4.0). Not legal advice.