Sri Jeevan Singh Rawat v. State of Uttarakhand
- Court
- High Court of Uttarakhand
- Date of judgment
- 28 October 2026
- Judge
- Justice Pankaj Purohit
- Case number
- WPMS No. 3200 of 2026
- Result
- ALLOWED
Full judgment
UKHC010183972026
2026:UHC:9741
HIGH COURT OF UTTARAKHAND AT NAINITAL Writ Petition Misc. Single No.3200 of 2026 28th October, 2026
Sri Jeevan Singh Rawat
………Petitioner Versus
State of Uttarakhand and others ………Respondent ---------------------------------------------------------------------Presence:Mr. K.K. Harbola, learned counsel for the petitioner. Mr. Suyash Pant, learned S.C. for the State.
---------------------------------------------------------------------Hon’ble Pankaj Purohit, J. Petitioner is a contractor who was awarded three contracts:A.
B.
C.
2.
Patch Repair Work in Km. 105.00 to 108.600 on NH 87 Ext. (New NH-109) under deposit 2023-24 in the state of Uttarakhand which was completed on 29-06-2024 and the same was measured by the department on 03-07-2024, total bill sanctioned of the said work is Rs. 2,46,671/Re-construction of R/Wall at Km. 107 (0-2) & 113 (4-6), Edge Wall at Km 111 & 112 and catch pit on NH-87 Ext (New NH-109) in the state of Uttarakhand, which was completed on 15-09-2024 and the same was measured by the department on 15-09-2024, total bill sanctioned of the said work is Rs.4,95,740/Construction of C.C. Drain at Km. 111.00 to 113.00 on NH-87 Ext (New NH-109) in the state of Uttarakhand, which was completed on 24-02-2024 and the same measured by the department on 2402-2024, total bill sanctioned of the said work is Rs.4,90,502/The petitioner completed the aforesaid work way
back in the year 2024 on different dates and for that work he was never paid a single penny. 3.
According to learned counsel for the petitioner for
the aforesaid three works an amount of ₹12,32,914/- is pending with the respondent-Department since 2024.
UKHC010183972026
2026:UHC:9741
4.
The petitioner made an averment in the writ
petition that dues payable to him is admitted by the respondent-Department and the Department be directed to make payment to the petitioner. 5.
This Court vide order dated 14.10.2026 directed
the State counsel to get instructions in the matter that as to whether dues are admitted or not. 6.
Today,
learned
State
counsel
passed
on
instructions to this Court dated 22.10.2026, which are taken on record and on the basis of said instructions submitted that dues are admitted and the petitioner has to be paid an amount of ₹12,32,914/- but due to non-availability of funds the said payment could not be made so far. 7.
It is also mentioned in the instructions that as and
when the budget would be available the amount due to the petitioner shall be disbursed to him. 8.
Having considered the rival submission of the
parties and having gone through the instructions very carefully, this Court is of the view that once the respondentDepartment sees that dues are admitted and the petitioner is entitled to get the same from the respondent-Department. Withholding of the dues would create unnecessary loss to the petitioner, who is a petty contractor. 9.
In such view of the matter, writ petition stands
allowed. Respondent no.4 is directed to make payment of the admitted dues of ₹12,32,914/- to the petitioner within a period of four months from the date of production of certified copy of this order.
(Pankaj Purohit, J.) 28.10.2026
SK
SHUBHAM KAPRUWAN
Digitally signed by SHUBHAM KAPRUWAN DN: c=IN, o=HIGH COURT OF UTTARAKHAND, ou=HIGH COURT OF UTTARAKHAND, 2.5.4.20=a29a2f80b93835a432d093afc472d9355959ee0ff878380c645e17d546a24821, postalCode=263001, st=UTTARAKHAND, serialNumber=B505B049BA2FDAC35E7AE325DEE1505D6C35AF3D290C229CDC609D61801E 1E4F, cn=SHUBHAM KAPRUWAN Date: 2026.10.28 19:38:50 +05'30'