IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 27TH DAY OF OCTOBER, 2026 PRESENT THE HON'BLE MRS. JUSTICE ANU SIVARAMAN AND THE HON'BLE MR. JUSTICE K.S.BHARATH KUMAR WRIT PETITION NO. 29075 OF 2025 (GM-RES-PIL) BETWEEN: SRI. SHARANAPPA GOUDA S/O GOLAPPA GOWDA AGE ABOUT 64 YEARS R/A H NO 5-11-113/2 MAIN ROAD NEAR POST OFFICEK MUDNAL LAYOUT YADGIR CITY YADGIR 585202

…PETITIONER Digitally signed by PAVITHRA N Location: High Court of Karnataka

(BY SRI. SANDEEP LAHIRI, ADVOCATE) AND: 1.

THE STATE OF KARNATKAA REP BY ITS SECRETARY PUBLIC WORKS DEPARTMENT MS BUILDING BANGALORE 560001

2.

THE PUBLIC WORKS KDEPARTMENT DIVISION OFFICE YADAGIRI YADIGIRI KARNATAKA 585202 REP BY THE EXECUTIVE ENGINEER

-2HC-KAR

3.

SHREE BANADESHWAR CONSTRUCTION COMPANY PARTNERSHIP FIRM REP BY PARTNER CHIDANADAPPA KALEBELAGUNDI SWAMY VIVEKANANDA NAGAR YADAGIR 585202 …RESPONDENTS

(BY SMT. PRAMODHINI KISHAN, AGA FOR R1 & R2; SMT. DRITHI S. RAJASHEKAR, ADV. FOR SRI. RAJASHEKAR S., ADV. FOR R3) THIS WRIT PETITION IS FILED UNDER ARTICLES 226 & 227 OF CONSTITUTION OF INDIA, PRAYING TO ISSUANCE OF WRIT ORDER OR DIRECTION IN THE NATURE OF CERTIORARI OR ANY OTHER APPROPRIATE WRIT ORDER OR DIRECTION TO QUASH THE WORK ORDER DATED 22.04.2025 BEARING No. EE/PWD/DIVN.YDG/TS-3/2025-26/149

ISSUED

BY

THE

RESPONDENT No. 2 IN FAVOUR OF THE RESPONDENT No. 3 PURSUANT TO TENDER INVITING NOTIFICATION OF THE RESPONDENT No. 2 DATED 07.03.2025 BEARIGNG REFERENCE No.

PED/2024-25/BR/WORK_INDENT19928

KARNATAKA

PUBLIC

PROCUREMENT

ON

THE

PORTAL

FOR

"CONSTRUCTION OF BRIDGE ON YADGIR SAIDAPUR MDR AT CH 5.80KM AND CONSTRUCTION OF ROAD FROM CH 7.0 TO

-3HC-KAR

8.50 KM IN YADGIR TALUK, YADGIR DISTRICT (UNDER 5054 APPENDIX-E FOR THE YEAR 2024-25)" VIDE ANNEXURE-A.

THIS

PETITION,

COMING

ON

FOR

PRELIMINARY

HEARING, THIS DAY, JUDGMENT WAS DELIVERED THEREIN AS UNDER: CORAM: HON'BLE MRS. JUSTICE ANU SIVARAMAN and HON'BLE MR. JUSTICE K.S.BHARATH KUMAR ORAL JUDGMENT (PER: HON'BLE MRS. JUSTICE ANU SIVARAMAN) This writ petition is filed seeking the following reliefs:"a) Issuance of writ order or direction in the nature of certiorari or any other appropriate writ order or direction to quash the Work order dated 22.04.2025 bearing No.EE/PWD/Divn.Ydg/TS-3/2025-26/149 issued by the respondent No.2 in favour of the respondent No.3 pursuant to tender inviting Notification of the Respondent No.2 dated 07.03.2025 bearing reference No.PED/2024-25/BR/WORK_INDENT19928

on

the

Karnataka Public Procurement Portal for "Construction of Bridge on Yadgir Saidapur MDR at CH 5.80 KM and Construction of Road from CH 7.0 to 8.50 KM in Yadgir Taluk, Yadgir District(Under 5054 Appendix-E for the year 2024-25)" vide Annexure-A.

-4HC-KAR

b) Issue a writ of mandamus or any other appropriate writ, order or direction directing Respondent No.2 to

initiate

a fresh tender for the

work

of

"Construction of Bridge on Yadgir Saidapur MDR at CH 5.80 KM and Construction of Road from CH 7.0 to 8.50 KM

in

Yadgir

Taluk,

Yadgir

District(Under

5054

Appendix-E for the year 2024-25)" in accordance with law and by ensuring participation only of technically qualified and eligible contractors."

2. petitioner

We have heard the learned counsel for the writ as

well

as

the

learned

Government

Advocate

appearing for the respondents. 3.

The

learned

counsel

appearing

for

the

writ

petitioner submits that the writ petitioner is a permanent resident of Yadagiri Town, Yadagiri District, Karnataka and that he is interested in the subject matter of this writ petition, that is, with regard to the "Construction of Bridge on Yadgir Saidapur MDR". It is further submitted that the technical qualifications provided in the tender document specifically provides that the tenderer should have, in the past five years, satisfactorily completed as prime contractor for at least one similar work of value not less than Rs.333.19 lakhs. It is further

-5HC-KAR

submitted that the past experience which is required in the tender document would also include past experience in conduct of a similar work. It is therefore contended that the award of the tender to respondent No.3 was illegal and incorrect. 4.

The statement of objections has been placed on

record by respondents No.1 and 2 wherein it is specifically stated as follows:"8.

It

is

further

submitted

that

the

tender

notification and Standard Bid Document (KW-4) issued by Respondent No.2 on 07.03.2025 prescribes the eligibility criteria requiring execution of "similar works" and do not restrict eligibility, exclusively to contractors having prior experience in executing isolated or stand alone

bridge

works.

In

technical

and

contractual

interpretation, the term "similar work" encompasses works of comparable scope, nature and complexity, which in the present case includes: i) Culvert Construction(including multi-vent RCC box culverts), ii) Cross drainage structures, iii) Approach road formation, iv) Road construction and allied works. Therefore, the requirement of "similar work" is broad and inclusive, covering not only the bridge/culvert components but also associated infrastructure elements

-6HC-KAR

such as approach roads, CD works, and roadway development on either side of the structure. 9. tender

The contention of the petitioner that the mandates

standalone

exclusive

bridge

prior

experience

construction

is

in

therefore

misconceived and contrary to the express terms of the tender document. The petitioner has failed to appreciate that

bridge

engineering

or

culvert

execution,

construction, is

inseparably

in

practical

linked

with

approach roads, drainage arrangements, and associated roadway works, forming a unified project package."

5.

It is therefore contended that respondent No.3 had

the qualifications as provided in the tender document. It is further submitted that the construction of the bridge is complete and that the bridge has been in use at least for six months.

6.

Having considered the contentions advanced and in

view of the submissions made in the statement of objections and in view of the fact that the construction of the bridge which was the major component of the work is now complete, we are of the opinion that the prayers as sought for in this writ petition

-7HC-KAR

cannot be granted. The writ petition fails and the same is accordingly dismissed.

Sd/(ANU SIVARAMAN) JUDGE

Sd/(K.S.BHARATH KUMAR) JUDGE

RAK List No.: 1 Sl No.: 10

Related judgments

More Karnataka High Court judgments

Search all Supreme Court and High Court judgments

Reproduced from the official court copy published on eCourts (Indian Court Judgments open dataset, CC-BY-4.0). Not legal advice.