Sri Tatiparthy Venkata Swamy v. The State of Andhra Pradesh

Court
High Court of Andhra Pradesh
Date of judgment
25 October 2026
Judge
Justice Venkateswarlu Nimmagadda
Case number
WP No. 30593 of 2026
Result
DISPOSED OF NO COSTS
Acts & sections
Article 226 Constitution, Article 14 Constitution, Section 151 CPC

Download the official PDF

Full judgment

APHC010553202026

IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) MONDAY, THE 26th DAY OF OCTOBER 2026 PRESENT THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 30593 OF 2026 Between: 1. Sri Tatiparthy Venkata Swamy, Sto. Late Venkaiah, Aged about 55 years, proprietor of M/s. Ratnam Granite Colony,

Cutting and Polishing Industry, R/o. SC

Cheruvukommupalem Village, Pelluru Post,

Ongole, Prakasam

District. 523272 ...Petitioner AND 1. The State of Andhra Pradesh, Rep.by its Principal Secretary Government, Industries and

Commerce Department,

to the

Secretariat,

Velagapudi, Amaravati, Guntur District. 522238 2. The Andhra Pradesh Industrial Infrastructure Corporation Ltd, Rep by its Vice Chairman and Managing Director,

APIIC Towers, Mangalari, Guntur

District 522503 3.

The

Executive

Director,

Andhra

Pradesh

Industrial

Infrastructure

Corporation Ltd APIIC Towers, Mangalari, Guntur District. 522503 4. The Chief General Manager Asset Management, Andhra Pradesh Industrial Infrastructure Corporation Ltd 522503

APIIC Towers, Mangalari, Guntur District.

5. The Zonal Manager, Andhra Pradesh Industrial Infrastructure Corporation Ltd.

(APIIC), Zonal Office, Gollapudivari Street,

Opposite Nalluri

Apartments, Santhapeta, Ongole, Prakasam District. 523001 ...Respondents Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue a writ, order or direction more particularly one in the nature of WRIT

OF MANDAMUS declaring the action of the respondents,

particularly the 5th respondent, in issuing proceedings vide Lr.No. 20/PKM/GC-OGL/P.No. 391-A/2026-27/3540 and 3589 dated

11.09.2026

21.09.2026, restricting the extension of time for payment of the balance land cost of Rs.17,79,375/- in respect of

Plot No.391-A, admeasuring 5745.00

Sq.Mts., at Growth Centre, Ongole, to only one month, up to 10.10.2026, as arbitrary, unreasonable and violative of Article 14 of the Constitution of India, and consequently direct the competent respondent authority to consider and grant the petitioner a further period of one year for land cost together with applicable interest resume the allotment of the said

payment of the balance

and GST, and not to cancel or

plot solely on the ground of non-payment

within the aforesaid period, and pass IA NO: 1 OF 2026 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased pleased to direct

the respondents particularly the 5th respondent not to

cancel or resume the allotment of Plot No.391-A, Growth Centre, Ongole, or take coercive or consequential action pursuant to the impugned proceedings vide Lr.No. 20/PKM/GC-OGL/P.No. 391-A/2026 11.09.2026 & 21.09.2026, solely on the

27/3540 and 3589 dated

ground of non-payment by

10.10.2026, pending disposal of the Writ Petition, and pass Counsel for the Petitioner: KISHORE KUMAR KATARI

Counsel for the Respondents: GP FOR INDUSTRIES COMMERCE The Court made the following order:

THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 30593 OF 2026 ORDER: The present Writ Petition is filed under Article 226 of the Constitution of India seeking following relief: “to issue a writ, order or direction more particularly one in the nature of WRIT OF MANDAMUS declaring the action of the respondents,

particularly

proceedings

vide

the

5th

respondent,

in

issuing

Lr.No.20/PKM/GC-OGL/P.No.391-A/2026-

27/3540 and 3589 dated 11.09.2026 & 21.09.2026, restricting the extension of time for

payment of the balance land cost of

Rs.17,79,375/- in respect of Plot No.391-A, admeasuring 5745.00 Sq.Mts., at Growth Centre, Ongole, to only one month, up to 10.10.2026, as arbitrary, unreasonable and violative of Article 14 of the Constitution of India, and consequently direct the competent respondent authority to consider and grant the petitioner a further period of one year for payment of the balance land cost together with applicable interest and GST, and not to cancel or resume the allotment of the said plot solely on the ground of non-payment within the aforesaid period, and pass such other order or orders…..”

2.

Heard learned counsel for the petitioner, learned Assistant Government

Pleader for respondent No.1 and Sri Santhi Chandra learned Standing counsel for APIIC for respondent Nos. 2 to 5. 3.

The case of the petitioner is that the petitioner herein was allotted the

land admeasuring to an extent of 5745.00 Sq.Mts. in Plot No.391-A situated in Growth Centre, Ongole in the year 2010 for establishment of Granite Cutting and Polishing Industry on ORS basis. Even after lapse of five years, the

petitioner was unable to implement the project as per the terms of the allotment/agreement. Subsequently, the said agreement was cancelled. Again, the petitioner herein resubmitted his application seeking re-allotment of the subject land to implement the same project for which the allotment was already made basing upon the fresh terms and conditions. Considering the request of the petitioner, again, the respondents re-allotted the subject land and insisted schedule of payment for registration of the subject property in favour of the petitioner. Accordingly, the petitioner paid 25% of the total land cost. Considering the said payment, the petitioner as well as the respondents entered into an agreement vide registered sale agreement dated 07.11.2024. As per the terms of the agreement, the petitioner herein has to deposit the remaining 75% amount i.e., Rs.17,79,375/- out of the total land cost with interest @4% per annum from 91st day to 180 days and with interest @8% p.a., from 181st day and within a period of two years from the date of issue of provisional re-allotment orders and get it registered the subject land in his favour. As per Clause 3 of the agreement, the entire project should be implemented within a period of three years from the date of agreement. While so, the respondent authorities, more particularly, the respondent No.2 issued a show cause notice dated 11.09.2026 after completion of entire two years period requesting the petitioner to pay the land cost of Rs.17,79,375/- within a period of one month along with interest. But the petitioner herein neither paid any amount as demanded nor submitted any explanation. Thereafter the respondents issued another proceedings on 21.09.2026 directing the

petitioner to pay the demanded amount on or before 10.10.2026 for compliance of the terms of the agreement. But till date the respondents neither paid any amount nor submitted any explanation but filed the present Writ Petition seeking extension of time for payment of the demanded amount. 4.

The learned Standing Counsel for the respondents furnished written

instructions reiterating the contentions what were stated at notices dated 21.09.2026 and 11.09.2026. It is further stated that the petitioner did not come forward to submit any other schedule of payment or seeking any indulgence of the respondents for extension of time. Moreover, the petitioner is unable to assign reasons for the delay caused in payment of the balance amount as demanded as per the terms of the agreement. She further submits that the petitioner is unable to pay the even registration amount to conclude the registration and when the project will be implemented, would be in question. 5.

Heard both the learned counsel and perused the material placed on

record, more particularly, the written instructions, it is observed that there are no reasonable grounds explained by the petitioner for defaulting payment as per the schedule of payment as agreed by the petitioner. It is further observed that the petitioner did not submit any explanation/reply to the notices issued by the respondents praying any defense for delay in making payment or assigned any reasons for not complying with the terms of the agreement. In the absence of any reasons for non-compliance of the terms of the agreement, the respondents are entitled to proceed further as per the terms of the

agreement dated 07.11.2024 read with notices dated 11.09.2026 and 21.09.2026. 6.

However, in view of the submissions of the learned counsel for the

petitioner, this Court is inclined to dispose of the Writ Petition, directing the petitioner to pay 50% amount out of the total balance amount of Rs.17,79,375/- along with GST and interest within a period of four (04) weeks from today and remaining entire amount within a period of four (04) weeks, thereafter. After such payment, the respondents are directed not to take any coercive steps. Failing which, even in respect of payment 1st installment of 50% amount, the respondents are at liberty to proceed further in accordance with the terms of the agreement as well as in accordance with law. 7.

With the above directions, the writ petition is disposed of. There shall be

no order as to costs. As a sequel, miscellaneous petitions, if any, pending shall stand closed.

__________________________________________________

JUSTICE VENKATESWARLU NIMMAGADDA Date: 26.10.2026 NOTE: C.C. by 28.10.2026 (B/o) BSP

THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA

WRIT PETITION NO: 30593 OF 2026

Date: 26.10.2026 NOTE: C.C. by 28.10.2026 (B/o) BSP

Related judgments

More Andhra Pradesh High Court judgments

Search all Supreme Court and High Court judgments

Reproduced from the official court copy published on eCourts (Indian Court Judgments open dataset, CC-BY-4.0). Not legal advice.