Dharmaraj Sadashiv Tisge v. The Union of India Through the Deputy Secretary and Others

Court
Bombay High Court
Date of judgment
2 November 2026
Case number
WP No. 15401 of 2026
Result
DISPOSED OFF
Acts & sections
Section 34 Arbitration Act
Subject
Property & land, Arbitration

Download the official PDF

Full judgment

2026:BHC-AUG:53895-DB

{1} drp

IN THE HIGH COURT OF JUDICATURE OF BOMBAY BENCH AT AURANGABAD WRIT PETITION NO.15401 OF 2026

Dharamraj Sadashiv Tisge

PETITIONER

VERSUS The Union of India and Others

RESPONDENTS

....... Mr. Vikrant P. Raje, Advocate for the Petitioner Mr. N. D. Batule, AGP for Respondent - State Ms. A. S. Jadhav, Advocate for Respondent No.4 ....... [CORAM : NITIN B. SURYAWANSHI, & ABASAHEB D. SHINDE, J. J.] DATE : 2nd NOVEMBER, 2026 ORDER : 1.

A copy of the decision of the Hon’ble Apex Court in the

Review Petition filed in the matter of “National Highways

Authority of India vs. Tarsem Singh and others” in Review Petition (Civil) No. 2528 of 2025 has been placed on record. Perusal of the said order, reveals that the Review Petition is disposed of by issuing following directions : “14.Considering the facts and circumstances explained in the instant proceedings along with the various submissions placed on record and with a view to balancing the equities regarding delay and the entitlements of the landowners, we issue the following directions:

{2} (i)

All landowners whose claims re: the quantum and/or components of compensation for their lands acquired under the NH Act were alive on or after 28.03.2008, i.e., they were pending before one of the prescribed fora, shall be entitled to seek addition of 'interest', 'solatium', and 'interest on the solatium' to their compensation claim;

(ii)

In the cases where compensation claims are alive on the aforesaid date, but the landowner has claimed "interest'". 'solatium', and 'interest on solatium' after 28.03.2008, no interest on both components shall be payable for the

period of delay. Such

landowner shall be entitled to 'Interest' and 'Interest on solatium' only from the date on which such claims were raised; and (iii)

If the claims of the landowners stood concluded prior to 28.03.2008, with no further appeal, Writ Petition, Special Leave Petition, etc., then such landowners are not entitled to seek reopening, review, or modification of the said decision for the purpose of claiming 'solatium' or 'interest'.”

2.

Indisputably, the issue raised in this petition and the

prayers made are squarely covered by the decision of the Coordinate Bench of this Court in Writ Petition No. 13783 of 2025 in the case of “Prakash Dayaram Patil Devre vs. The Competent

Authority Land Acquisition and Another” and connected matters. In view of the principles enunciated in the case of “Union of India

(UOI) and Ors. Vs. Tarsem Singh and Ors”. reported in 2019 (9) SCC 304, we pass the following order :

{3}

ORDER a)

The writ petition is allowed by directing the competent authority to compute and pay to the petitioner solatium and interest in accordance with the principles enunciated in the case of “Union of India and another Vs. Tarsem Singh and

others” (Supra) within a period of six (6) months from today. (b) It is made clear that the petitioner shall assist the competent authority by producing all relevant documents and upon verification of the same, the competent authority shall proceed further. It is also clarified that payments made pursuant to the directions given herein above, shall be subject to the challenges, if any, raised under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.

(c) In the light of the observations made herein above, it is further made clear that if the petitioner is aggrieved by the quantum and computation carried out by the competent authority while carrying out the directions given herein above, the remedy of Section 3G (5) of the National Highways Act, 1956 would be available to such aggrieved party in accordance with law. It is further made clear that the competent Authority while implementing the directions

{4}

given herein above shall give reasonable hearing to all stake holders. 3.

As observed by this Court in clause ‘C’ (supra), if any party

has

any

objection

in

respect

of

the

calculation

of

the

compensation amount, they are at liberty to approach Arbitrator under Section 3G (5) of the National Highways Act.

[ ABASAHEB D. SHINDE ] JUDGE drp/wp15401-26.doc

[ NITIN B. SURYAWANSHI ] JUDGE

Related judgments

More Bombay High Court judgments

Search all Supreme Court and High Court judgments

Reproduced from the official court copy published on eCourts (Indian Court Judgments open dataset, CC-BY-4.0). Not legal advice.