M/S Supreme Bkb Deco Jv (joint Venture Entity), Thro Its Authorized Signatory Mukesh Kumar Singh v. Rites Limited, Through the Chairman-Cum-Managing Director

Court
High Court of Jharkhand
Date of judgment
4 November 2026
Judge
Justice Manoj Prasad
Case number
C.M.P. No. 1102 of 2026
Result
Disposed Off
Acts & sections
Section 34 Arbitration Act
Advocates
Sumeet Gadodia, Anish Lal, Srijit Chaudhary, Khalida Haya Rashmi, Ayush Kumar
Subject
Civil, Arbitration

Download the official PDF

Full judgment

Neutral Citation No. (2026:JHHC:32406-DB)

IN THE HIGH COURT OF JHARKHAND AT RANCHI C.M.P. No. 1102 of 2026 --------M/s Supreme BKB Deco JV (Joint Venture Entity), having its Head Office at Surya Auto Campus, Dhansar, P.O. & P.S. Dhansar, District Dhanbad, PIN-828106 (Jharkhand), through its Authorized Signatory namely, Mukesh Kumar Singh, aged about 47 years, son of Shiv Nandan Prasad Singh, resident of House No.191 A6, Morabadi, P.O. R.M.C.H., P.S. Bariatu, District Ranchi, PIN-834009 (Jharkhand) ...

...

...

Petitioner

Versus 1. RITES Limited, through the Chairman-cum-Managing Director, having its office at Scope Minar, P.O. & P.S. Laxminagar, District Delhi, PIN-110092, having its Corporate Office at Rites Bhawan, Plot No.1, Sector 29, P.O. & P.S. Sector-29, District Gurgaon. 2. Damodar Vally Corporation, through its Chairman, having its office

at DVC Towers, VIP Road, Kolkata, P.O. & P.S. Ultadanga, District Kolkata, PIN-700054 (West Bengal) …. .… ...

Respondents

--------CORAM: HON’BLE THE CHIEF JUSTICE HON’BLE MR. JUSTICE MANOJ PRASAD --------For the Petitioner : Mr Sumeet Gadodia, Advocate Mr Anish Lal, Advocate For the Respondents : Mr Srijit Chaudhary, Advocate Ms Khalida Haya Rashmi, Advocate Mr Ayush Kumar, Advocate --------Order No.03/ Dated: 04.11.2026 Per : M.S. Sonak, C.J.

1. Heard learned counsel for the parties. 2. The rule is made returnable immediately with the consent and at the

request of the learned counsel for the parties.

3. The petitioner seeks expeditious disposal of Commercial Execution

Case No.03 of 2026 pending before the Commercial Court at Ranchi for execution of arbitral award dated 06.08.2025. 4. Mr Gadodia, the learned counsel for the petitioner, contends that the

respondents have filed an application under Section 34 of the Arbitration and Conciliation Act, 1996 (said Act) to challenge the arbitral award dated 06.08.2025. However, to date, the office objections remain uncleared. He points out that no stay has been granted by the Commercial Court. He submitted that since no stay has been granted, the execution proceedings must proceed, given the decisions of the Hon’ble Supreme Court in the cases of Rahul S. Shah Vs. Jitendra Kumar Gandhi reported in (2021) 6 SCC 418, Chopra Fabricators & Manufacturers Pvt. Ltd. Vs. Bharat Pumps and Compressors Limited and another reported in (2023) 3 SCC 534 and Bhoj Raj Garg Vs. Goyal Education and Welfare Society & Others reported in (2022) SCC OnLine SC 2449 and other matters. 5. Mr Srijit Choudhary, appearing with Ms Khalida Haya Rashmi for

the respondents, submitted that no application has been filed by the petitioner with the Executing Court seeking expeditious disposal of the execution proceedings. They pointed out that the petition under Section 34 of the said Act seeks a stay. They further pointed out that the objections remain unaddressed for reasons beyond the respondents' control. Accordingly, they submitted that this petition should be dismissed.

6. The rival contentions now fall for our determination. 7. The award of which execution is applied for was made on

06.08.2025. The execution was applied for on 7th April 2026. From what is placed before us, it appears that the execution is not proceeding at the required pace. 8. Merely because a Section 34 application is filed by the respondents

or an application for stay on the execution of the arbitral award is filed by the respondents, as long as no stay is granted, the Executing Court should not delay the execution proceedings. Mere pendency of a Section 34 application does not operate as an automatic stay on the execution of the arbitral award. This position has been clarified both legislatively and by precedents. 9. In Rahul S. Shah (supra), the Hon’ble Supreme Court has held that

the Executing Court must dispose of execution proceedings within six months from the date of their filing, which may be extended only by recording reasons in writing for the delay. 10. In Chopra Fabricators (supra), the Hon’ble Supreme Court

emphasised the need to dispose of execution cases expeditiously, especially in relation to arbitral awards. 11. Even the other decisions cited by Mr Gadodia repeat and reiterate

that there should be no delay in disposal of execution proceedings and such execution proceedings must be disposed of within six months from the date of filing unless there are unavoidable reasons, which, again, should be recorded in writing.

12. The record in this case shows that the Executing Court has tagged

Commercial Execution Case No.03 of 2026 and the respondents’ application under Section 34 of the said Act together, and the matter is being adjourned because the respondents have not yet cleared the defects pointed out by the Registry in the Section 34 application. This is not proper. The respondents must take all necessary steps to move the Commercial Court and obtain interim reliefs, if entitled, whether conditionally or unconditionally. 13. However, if no interim relief is obtained and execution of the award

is not stayed, the Executing Court cannot defeat the Hon’ble Supreme Court's repeated directions by clubbing two matters. 14. The Learned counsel for the respondents surprisingly wish to argue

on the defects pointed out by the Registry by contending that there are no defects at all or that the Registry of the Court is itself to be blamed. 15. We have been shown the records as reflected on the Commercial

Court website. The record shows that for the last twelve dates, the matter has been adjourned for removal of defects. Therefore, based on such submissions, the respondents cannot be allowed to delay the execution proceedings. 16. If, as the respondents contend, the office objections cannot be

cleared by them for reasons beyond their control, they must apply to the Commercial Court for a waiver of such office objections. However, the respondents cannot resist the execution proceedings

and, on the other hand, fail to clear the office objections and secure a stay on execution of the arbitral award. 17. Considering the above circumstances and the decisions of the

Hon’ble Supreme Court regarding expeditious disposal of the execution proceedings within six months from the date of their institution, we direct the Executing Court to dispose of Commercial Execution Case No. 03 of 2026 as expeditiously as possible and in any event, within three months from today, unless, of course, in the meantime, the execution of the arbitral award is stayed. 18. This C.M.P. is disposed of in the above terms without any order for

costs. (M. S. Sonak, C.J.) (Manoj Prasad, J.) November 4th , 2026 BS/Madhav/-