M/S Umed Singh Adhikari v. State of Uttarakhand

Court
High Court of Uttarakhand
Date of judgment
28 October 2026
Judge
Justice Pankaj Purohit
Case number
WPMS No. 3291 of 2026
Result
DISPOSED

Download the official PDF

Full judgment

UKHC010188782026

COURT’S OR JUDGE’S ORDERS

.SL. No.

Date

Office Notes, reports, orders or proceedings or directions and Registrar’s order with Signatures

2026:UHC:9755

WPMS/3291/2026 M/s Umed Singh Adhikari

--Petitioner

Versus State Of Uttarakhand & others

--Respondents

Hon'ble Pankaj Purohit, J.

Mr. Naitik Bhatt, learned Counsel for petitioner.

2.

Mr. Yogesh Pande, learned Dy.A.G. for the State.

3.

Petitioner, who is a Contractor by profession, was

awarded two contracts in the year 2024 and 2025 for reconstruction of damaged wall situated at 132 Kms (8-10) on the NH 87 Ext. (New NH-109) at Village Malli Mirai, Dwarahat, Tehsil

Dwarahat,

District

Almora.

The

said

work

was

completed by the petitioner within time. 4.

Learned counsel for the petitioner submits that he has

not been paid a single penny for the work done by him and accordingly a sum of Rs.4,92,940.82 and Rs.4,98,795.92 is pending with the respondent-Department since the year 2024 and 2025 respectively. 5.

The petitioner submitted in the writ petition that dues

payable to the petitioner are admitted by the respondentDepartment. 6.

This Court vide order dated 27.10.2026 had directed the

State counsel to get instructions as to whether the dues claimed by petitioner are admitted to them or not. 7.

Today, instructions have been produced before this

Court by learned State Counsel which are taken on record. 8.

In paragraph no. 2 of the said instructions, it has been

stated

that

the

dues

are

admitted

to

the

extent

of

UKHC010188782026

2026:UHC:9755

Rs.4,72,292/- and Rs.4,89,889/- total Rs.9,62,181/-. The reason for non-payment is cited as non-availability of the budget, and it is further stated that payment will be made to the petitioner as and when the budget is received. 9.

Having considered the rival submission of the parties

and having gone through the instructions carefully, this Court is of the view that once the respondent-department contends that the dues are admitted to them which the petitioner is entitled to get, therefore, withholding such dues would create unnecessary financial loss to the petitioner, who is a Contractor. 10.

In such view of the matter the writ petition stands

allowed. The respondent no.1 is directed to make payment of the admitted dues i.e., Rs.4,72,292/- and Rs.4,89,889/- total Rs.9,62,181/- to the petitioner within a period of four months from the date of production of certified copy of this order.

R.Dang

(Pankaj Purohit, J.) 28.10.2026