Prabhulal Lalji Thakkar and Anr v. Municipal Corporation of Greater Mumbai

Court
Bombay High Court
Date of judgment
22 October 2026
Case number
CONPW No. 88 of 2024
Result
DISPOSED OFF

Download the official PDF

Full judgment

NISHA SANDEEP CHITNIS Digitally signed by NISHA SANDEEP CHITNIS Date: 2026.10.23 17:37:48 +0530

IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION CONTEMPT PETITION NO.88 OF 2024 IN WRIT PETITION NO.2514 OF 2015

Prabhulal Lalji Thakkar and Anr. Versus Municipal Corporation of Greater Mumbai and Ors.

...Petitioners

...Respondents

Mr. Siddhant Trivedi with Mr. Aayu Saxena, Mr. Aayush Modi, Mr. Ashray Dave and Ms. Hritika Shroff, for the Petitioners Ms. Shweta Patankar h/f Mr. Shailendra Sardar i/b Ms. Komal Punjabi for the Respondent No.1– M.C.G.M. Mr. Yash Tiwari with Mr. Dawood Chauhan for the Respondent Nos.2 and 3.

CORAM: BHARATI DANGRE & ASHISH S. CHAVAN, JJ. DATE

:

22nd OCTOBER 2026

P.C. : 1.

The Contempt Petition alleges disobedience of the order

passed by the Division Bench of this Court on 31 st March 2023, wherein this Court recorded that the petitioners were ready and willing to enter into a Permanent Alternate Accommodation Agreement (PAAA) with respondent Nos. 2 and 3, and the learned

1/3

counsel representing respondent Nos. 2 and 3 also expressed a consensus. He further made a statement that the agreement would be entered into within a period of four weeks from the date of passing of the order.

2.

The Contempt Petition alleges disobedience of the

aforesaid order on the ground that, despite the undertaking given by the learned counsel representing respondent Nos. 2 and 3 that such an agreement would be entered into within a period of four weeks, the stipulated timeline has not been adhered to.

3.

The learned counsel for the petitioners himself invites our

attention to a communication dated 21st August 2023, enclosing a draft of Agreement for Permanent Alternate Accommodation. However, the petitioners responded by stating that the draft agreement was not in consonance with the understanding arrived at, and that the statement made before this Court was on the basis that the PAAA to be executed in their favour would be on an ownership basis.

2/3

4.

In our view, the aspect of providing the PAAA on an

ownership basis was not agreed to by respondent Nos. 2 and 3 when the order was passed on 31 st March 2023. What was agreed to by respondent Nos. 2 and 3 was only that a PAAA would be entered into within a period of four weeks. In these circumstances, we are of the view that the alleged disobedience cannot be said to be wilful, particularly when a draft agreement was exchanged but the petitioners did not agree to its terms and conditions. We, therefore, find no reason to proceed further with the contempt proceedings against the respondents and drop the same.

ASHISH S. CHAVAN, J.

BHARATI DANGRE, J.

3/3

Related judgments

More Bombay High Court judgments

Search all Supreme Court and High Court judgments

Reproduced from the official court copy published on eCourts (Indian Court Judgments open dataset, CC-BY-4.0). Not legal advice.